When taking a field sample of fresh concrete for slump, air, and cylinders, which portion of the load is generally the best source?

  1. The very first concrete discharged
  2. The very last concrete discharged
  3. A representative sample from the middle portion of the discharge
  4. Concrete scraped from the hopper after discharge ends

Answer: C — A representative sample from the middle portion of the discharge