Practice question

A driven pile reaches the specified blow count well above the planned cutoff elevation, leaving the tip elevation higher than expected. What should the inspector do?

  1. Accept the pile immediately and cut it off without notice
  2. Drive the pile until the cutoff elevation is reached regardless of resistance
  3. Document the condition and get engineering direction before accepting final disposition
  4. Cut the pile and weld an extension later if needed without approval

Answer: C — Document the condition and get engineering direction before accepting final disposition

The correct answer is shown above. Try the full quiz for additional practice.