A driven pile reaches the specified blow count well above the planned cutoff elevation, leaving the tip elevation higher than expected. What should the inspector do?
- Accept the pile immediately and cut it off without notice
- Drive the pile until the cutoff elevation is reached regardless of resistance
- Document the condition and get engineering direction before accepting final disposition
- Cut the pile and weld an extension later if needed without approval
Answer: C — Document the condition and get engineering direction before accepting final disposition