Practice question
Just before concrete placement, several rebar chairs tip over and the top mat is resting too low, reducing clear cover. What should the inspector require?
- Place the concrete anyway because the bars will float up
- Stop placement in that area and reset the steel to the required position
- Pour the concrete and correct the cover by extra curing
- Cut out a few bars so the mat sits flatter
Answer: B — Stop placement in that area and reset the steel to the required position
The correct answer is shown above. Try the full quiz for additional practice.