Before epoxy-coated reinforcing steel is incorporated into the work, what is one key acceptance check on the paperwork?
- Confirm the certification matches the delivered bar size, grade, and identification
- Check that the paperwork is signed by the truck driver only
- Confirm the bars were fabricated at the nearest plant
- Verify the bars were delivered on the same day they were coated
Answer: A — Confirm the certification matches the delivered bar size, grade, and identification