According to the Hot-Mix Asphalt Paving Handbook compaction sequence, where should the breakdown roller operate?
- Several hundred feet behind the paver after the mat has set
- Immediately behind the paver while the mix is still hot and workable
- Only after the finish roller has removed the marks
- Only on the cold joint after the adjacent lane is placed
Answer: B — Immediately behind the paver while the mix is still hot and workable
The correct answer is shown above. Try the full quiz for additional practice.