Practice question

Per NMDOT 2019 Section 203.2.1.3, borrow is Contractor-provided suitable embankment material obtained from:

  1. Unclassified excavation still available inside the right of way
  2. An approved source outside the right of way, unless the Contract says otherwise
  3. Any convenient roadside ditch without approval
  4. Milled asphalt pavement stockpiled on the project

Answer: B — An approved source outside the right of way, unless the Contract says otherwise

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NM CID GA-1 Practice Questions - New Mexico CID GA-1 Streets, Roads and Highways Examination Exam →