On-site cut yields 4,500 BCY of soil that shrinks 10 percent. The project needs 5,000 CCY of embankment. How much additional borrow (bank cubic yards) is required if the borrow also shrinks 10 percent?

  1. 500 BCY
  2. 556 BCY
  3. 1,000 BCY
  4. 1,056 BCY

Answer: D — 1,056 BCY

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NM CID GA-1 Practice Questions - New Mexico CID GA-1 Streets, Roads and Highways Examination Exam →
Learndmv.

Thoughtful practice for the road ahead. Find permit, road signs and CDL preparation by state.

Explore

Practice by stateAll practice testsExam types

Your account

My profilePractice historyAccount security

Get started

Create accountSign inSitemap
© 2026 LearndmvIndependent practice resource · Not affiliated with any state DMV.