On-site cut yields 4,500 BCY of soil that shrinks 10 percent. The project needs 5,000 CCY of embankment. How much additional borrow (bank cubic yards) is required if the borrow also shrinks 10 percent?
Answer: D — 1,056 BCY
The correct answer is shown above. Try the full quiz for additional practice.