Practice question
Per NMDOT 2019 Division 100, time extensions are granted only to the extent that Delay impacts activities on which part of the Baseline Schedule?
- Any activity the Contractor chooses
- The Critical Path of the Baseline Schedule in effect at the time of the Delay
- Only punch-list work
- Only material-delivery activities off the project
Answer: B — The Critical Path of the Baseline Schedule in effect at the time of the Delay
The correct answer is shown above. Try the full quiz for additional practice.