Per NMDOT 2019 Division 100, time extensions are granted only to the extent that Delay impacts activities on which part of the Baseline Schedule?

  1. Any activity the Contractor chooses
  2. The Critical Path of the Baseline Schedule in effect at the time of the Delay
  3. Only punch-list work
  4. Only material-delivery activities off the project

Answer: B — The Critical Path of the Baseline Schedule in effect at the time of the Delay

The correct answer is shown above. Try the full quiz for additional practice.