Practice question

Per NMDOT 2019 Section 203.5.1, if the Contractor stockpiles excavated material a second time only for the Contractor's convenience, how is the second handling paid?

  1. At the unclassified-excavation unit price again
  2. As extra work under Section 109
  3. There will be no additional cost to the Department
  4. At 50 percent of the borrow unit price

Answer: C — There will be no additional cost to the Department

The correct answer is shown above. Try the full quiz for additional practice.