EPA stormwater construction guidance and NMDOT Section 603 require the Contractor to implement erosion and sediment controls in accordance with which project document?

  1. Only the asphalt job-mix formula
  2. The accepted Stormwater Pollution Prevention Plan (SWPPP)
  3. The concrete cylinder-break report
  4. The dump-truck tailgate policy

Answer: B — The accepted Stormwater Pollution Prevention Plan (SWPPP)