Practice question

To keep sediment from being tracked onto a public highway, EPA construction BMPs and NMDOT Section 603 expect the Contractor to provide:

  1. A silt fence across the travel lane
  2. A stabilized construction exit (typically a rock tracking pad) at the point vehicles leave the disturbed site
  3. A fog seal on the haul road clay
  4. Only a sweeper after the project is complete

Answer: B — A stabilized construction exit (typically a rock tracking pad) at the point vehicles leave the disturbed site

The correct answer is shown above. Try the full quiz for additional practice.