Practice question
Per NMDOT 2019 606.3.1.1.1, after compacting a post leave-out, the Contractor shall place how much Section 303 Base Course and apply emulsion within what time?
- 8 inches of Base Course, with emulsion within 7 days
- 1 inch of cold mix only, with no emulsion required
- 6 inches of concrete, with no time limit
- 3 inches of Base Course, with emulsion within 24 hours of compaction
Answer: D — 3 inches of Base Course, with emulsion within 24 hours of compaction
The correct answer is shown above. Try the full quiz for additional practice.