Practice question

Per NMDOT 2019 606.5.1, which of the following is included in the guardrail or end-treatment price and is not measured separately?

  1. End Terminals, which are never a separate bid item
  2. Overhead sign structures
  3. Hot-mix major paving under Section 423
  4. Offset blocks, post leave-outs, connecting hardware, and asphalt curbs

Answer: D — Offset blocks, post leave-outs, connecting hardware, and asphalt curbs

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: NM CID GA-5 Practice Questions - New Mexico CID GA-5 Highway Signs and Guard Rails Examination Exam →