Per NMDOT 2019 701.5.1, which work is included in the traffic-sign pay items and not paid separately?
- Traffic Control Management under Section 618
- Hardware; excavation, backfill, and compaction; Class A concrete for extruded-panel foundations and multi-directional slip-base posts; and hauling of removals and salvage
- Overhead sign structure foundations, which are never paid under any section
- Steel reinforcement for overhead sign foundations, which is always incidental to the panel
Answer: B — Hardware; excavation, backfill, and compaction; Class A concrete for extruded-panel foundations and multi-directional slip-base posts; and hauling of removals and salvage
The correct answer is shown above. Try the full quiz for additional practice.