Per NMDOT 2019 618.2.2, the traffic control supervisor's only responsibility is traffic-control management, except when:
- The Project is small and requires limited traffic control, and the Project Manager and District Traffic Engineer approve the exception at the Pre-Construction Conference
- The TCS is also the Project superintendent on every NMDOT job
- Night work is underway
- A Subcontractor is providing the devices
Answer: A — The Project is small and requires limited traffic control, and the Project Manager and District Traffic Engineer approve the exception at the Pre-Construction Conference