Per NMDOT 2019 618.2.2, the traffic control supervisor's only responsibility is traffic-control management, except when:

  1. The Project is small and requires limited traffic control, and the Project Manager and District Traffic Engineer approve the exception at the Pre-Construction Conference
  2. The TCS is also the Project superintendent on every NMDOT job
  3. Night work is underway
  4. A Subcontractor is providing the devices

Answer: A — The Project is small and requires limited traffic control, and the Project Manager and District Traffic Engineer approve the exception at the Pre-Construction Conference

The correct answer is shown above. Try the full quiz for additional practice.