What are the four main components (zones) of a temporary traffic control zone for work zones according to the MUTCD?
- Buffer zone, work zone, taper zone, and detour zone
- Advance warning area, transition area, activity area, and termination area
- Construction area, flagging area, barrier area, and cleanup area
- Approach area, merge area, work area, and exit area
Answer: B — Advance warning area, transition area, activity area, and termination area