Practice question

On a mass-grading job, borrow material is:

  1. Excess cut hauled off the project as waste
  2. Fill imported from off-site because on-site cut is not enough
  3. Topsoil left in place under an embankment
  4. The swell portion of blasted rock only

Answer: B — Fill imported from off-site because on-site cut is not enough

The correct answer is shown above. Try the full quiz for additional practice.