A dozer is estimated at 60 bank cubic yards per hour. The crew works an 8-hour shift at 75 percent efficiency. What production should be planned for the shift?

  1. 360 bank cubic yards
  2. 450 bank cubic yards
  3. 480 bank cubic yards
  4. 640 bank cubic yards

Answer: A — 360 bank cubic yards

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: VA H H QI Practice Questions - Virginia Highway Heavy Contracting Qualified Individual Examination Exam →
Learndmv.

Thoughtful practice for the road ahead. Find permit, road signs and CDL preparation by state.

Explore

Practice by stateAll practice testsExam types

Your account

My profilePractice historyAccount security

Get started

Create accountSign inSitemap
© 2026 LearndmvIndependent practice resource · Not affiliated with any state DMV.