A storm line must drop 5.0 feet at a uniform 2.0 percent slope. What length of pipe is required?

  1. 100 feet
  2. 200 feet
  3. 250 feet
  4. 500 feet

Answer: C — 250 feet

The correct answer is shown above. Try the full quiz for additional practice.