Practice question

Proper pipe bedding and haunching are critical because they:

  1. Are only cosmetic and may be omitted under a paved street
  2. Support the pipe, control deflection of flexible pipe, and distribute load into the trench
  3. Replace the need to compact any backfill above the springline
  4. Allow the contractor to skip Virginia 811 locates

Answer: B — Support the pipe, control deflection of flexible pipe, and distribute load into the trench

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: VA H H QI Practice Questions - Virginia Highway Heavy Contracting Qualified Individual Examination Exam →