Practice question

Silt fence on a highway grading project is installed to:

  1. Replace the storm-sewer system
  2. Intercept sheet flow and filter sediment before it leaves the disturbed area
  3. Serve as a trench protective system under OSHA
  4. Mark the APWA color for proposed excavation

Answer: B — Intercept sheet flow and filter sediment before it leaves the disturbed area

The correct answer is shown above. Try the full quiz for additional practice.