After the marking period, an excavator arrives and sees clear evidence of an unmarked utility in the dig area. The correct action is to:

  1. Start digging carefully with a large bucket and hope the line is deep
  2. Make an additional contact with the notification center and not begin excavating until 3 hours later, after checking positive response
  3. Ignore the evidence if the original ticket number is still valid
  4. Paint over the evidence with white proposed-excavation paint

Answer: B — Make an additional contact with the notification center and not begin excavating until 3 hours later, after checking positive response