Practice question

In Virginia, a routine excavator notification is generally valid for how long from 7:00 a.m. on the next working day after the locate request?

  1. 48 hours only, with no possibility of working after that
  2. 15 working days
  3. One calendar year
  4. Until the H/H license expires

Answer: B — 15 working days

The correct answer is shown above. Try the full quiz for additional practice.