Before demolition begins, electric, gas, water, steam, sewer, and other service lines must be:

  1. Left live so the crew has power and water
  2. Shut off, capped, or otherwise controlled outside the building line, with involved utility companies notified in advance
  3. Marked with white paint only, then demolished live
  4. Disconnected only after the roof is removed

Answer: B — Shut off, capped, or otherwise controlled outside the building line, with involved utility companies notified in advance