The usual safe sequence for mechanical demolition of a multi-story structure is:
- Remove the foundation first so the building drops as a unit
- Work from the top down, taking upper floors before undermining supporting members below
- Cut all columns on the first floor simultaneously with no engineering controls
- Start in the center of the lowest floor and work outward
Answer: B — Work from the top down, taking upper floors before undermining supporting members below