Practice question

To measure parasitic draw on a parked school bus, a technician should connect the ammeter:

  1. In parallel across the battery posts
  2. Across the starter solenoid
  3. In series with the alternator output
  4. In series with a disconnected battery cable

Answer: D — In series with a disconnected battery cable

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: ASE S6 Electrical Electronic Systems (School Bus) Practice Questions - ASE S6 - Electrical Electronic Systems (School Bus) Certification Exam →