Practice question

Under Article 23(5) of the CMR Convention, if goods are delivered with a delay and the claimant proves that damage resulted from that delay, what is the MAXIMUM compensation the carrier can be held liable for?

  1. An amount not exceeding the total freight charges (carriage cost)
  2. Twice the commercial value of the cargo
  3. 8.33 SDR per kilogram of the entire shipment weight
  4. Full compensation for lost factory production profits without any ceiling

Answer: A — An amount not exceeding the total freight charges (carriage cost)

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: Austria BKF C95 Practice Questions - Austria Berufskraftfahrer Grundqualifikation C95 (Truck Driver Initial Qualification) Exam →