Practice question

On Caltrans highway construction projects, how is the core 'Traffic Control System' typically paid under contract bid items?

  1. Per cone placed per hour of active work.
  2. Per linear foot of traffic taper installed.
  3. Per square foot of warning sign surface.
  4. As a contract Lump Sum (LS) bid item.

Answer: D — As a contract Lump Sum (LS) bid item.

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: C-31 Traffic Control Practice Questions - California CSLB C-31 Construction Zone Traffic Control Examination Exam →