Practice question
On Caltrans highway construction projects, how is the core 'Traffic Control System' typically paid under contract bid items?
- Per cone placed per hour of active work.
- Per linear foot of traffic taper installed.
- Per square foot of warning sign surface.
- As a contract Lump Sum (LS) bid item.
Answer: D — As a contract Lump Sum (LS) bid item.
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: C-31 Traffic Control Practice Questions - California CSLB C-31 Construction Zone Traffic Control Examination Exam →