Practice question
How many days in advance must a C-31 contractor submit a proposed freeway lane closure schedule to the Caltrans District Traffic Manager (DTM)?
- 1 calendar day prior to planned implementation.
- 3 calendar days prior to planned implementation.
- 7 calendar days prior to planned implementation.
- 30 calendar days prior to planned implementation.
Answer: C — 7 calendar days prior to planned implementation.
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: C-31 Traffic Control Practice Questions - California CSLB C-31 Construction Zone Traffic Control Examination Exam →