How many days in advance must a C-31 contractor submit a proposed freeway lane closure schedule to the Caltrans District Traffic Manager (DTM)?

  1. 1 calendar day prior to planned implementation.
  2. 3 calendar days prior to planned implementation.
  3. 7 calendar days prior to planned implementation.
  4. 30 calendar days prior to planned implementation.

Answer: C — 7 calendar days prior to planned implementation.