Practice question

Prior to implementing a full road closure for a construction project, which agencies must the contractor notify first?

  1. The California Department of Fish and Wildlife.
  2. Local emergency services including police, fire, and EMS.
  3. The Regional Water Quality Control Board.
  4. The Federal Highway Administration regional office and state DOT coordination office.

Answer: B — Local emergency services including police, fire, and EMS.

The correct answer is shown above. Try the full quiz for additional practice.