When a scheduled lane closure is cancelled due to inclement weather, by what deadline must the contractor notify the Caltrans LCS?

  1. Within 24 hours after the scheduled closure end time.
  2. At least 48 hours before the end of the work week.
  3. Before the mandatory cancellation cutoff time specified by the DTM.
  4. No notification is necessary if rain is falling at the jobsite during scheduled closure times.

Answer: C — Before the mandatory cancellation cutoff time specified by the DTM.