Practice question
What is the proper sequence for removing temporary traffic control devices when picking up a highway lane closure?
- Remove devices starting in the advance warning zone and move downstream.
- Remove devices starting at the merging taper and move downstream into the work zone.
- Remove devices starting in the termination area and move upstream against traffic.
- Remove devices starting at the work activity area and move downstream.
Answer: C — Remove devices starting in the termination area and move upstream against traffic.
The correct answer is shown above. Try the full quiz for additional practice.