Practice question

What is the proper sequence for removing temporary traffic control devices when picking up a highway lane closure?

  1. Remove devices starting in the advance warning zone and move downstream.
  2. Remove devices starting at the merging taper and move downstream into the work zone.
  3. Remove devices starting in the termination area and move upstream against traffic.
  4. Remove devices starting at the work activity area and move downstream.

Answer: C — Remove devices starting in the termination area and move upstream against traffic.

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: C-31 Traffic Control Practice Questions - California CSLB C-31 Construction Zone Traffic Control Examination Exam →