Practice question

Under Caltrans Standard Plan T13 for moving lane closures (e.g., striping or pothole patching), what equipment setup is required?

  1. Concrete K-rail barriers installed along the entire length of the paint striping run.
  2. Type III barricades anchored to the pavement at 100-foot intervals.
  3. A train of shadow vehicles equipped with TMAs, arrow boards, and sign displays.
  4. Fixed advance warning signs mounted on timber posts every 500 feet.

Answer: C — A train of shadow vehicles equipped with TMAs, arrow boards, and sign displays.

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: C-31 Traffic Control Practice Questions - California CSLB C-31 Construction Zone Traffic Control Examination Exam →