Practice question

When original pavement markings conflict with temporary traffic lanes during long-term construction, what action must be taken?

  1. Conflicting markings may remain if drivers are attentive.
  2. Conflicting markings must be painted over with plain black oil paint.
  3. Conflicting markings must be removed or obliterated completely.
  4. Conflicting markings should be covered with clear plastic sheeting.

Answer: C — Conflicting markings must be removed or obliterated completely.

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: C-31 Traffic Control Practice Questions - California CSLB C-31 Construction Zone Traffic Control Examination Exam →