What is the primary objective of a post-test debriefing session led by a Certified Test Conductor?

  1. To assign blame for any test failures that occurred.
  2. To capture lessons learned, procedural issues, and anomalies to improve future tests.
  3. To provide immediate data analysis results to the project manager.
  4. To formally sign off on the final test report before it is written.

Answer: B — To capture lessons learned, procedural issues, and anomalies to improve future tests.