What is the primary objective of a post-test debriefing session led by a Certified Test Conductor?
- To assign blame for any test failures that occurred.
- To capture lessons learned, procedural issues, and anomalies to improve future tests.
- To provide immediate data analysis results to the project manager.
- To formally sign off on the final test report before it is written.
Answer: B — To capture lessons learned, procedural issues, and anomalies to improve future tests.