Practice question

When preparing a bid for a public works highway striping contract, how should a C-32 contractor account for the quantity of glass retroreflective beads?

  1. Calculate glass beads as 1.0 pound per gallon of waterborne paint.
  2. Calculate glass beads as 3.0 pounds per gallon of waterborne paint.
  3. Calculate glass beads as 4.5 pounds per gallon of waterborne paint.
  4. Calculate glass beads as 6.0 pounds per gallon of waterborne paint.

Answer: D — Calculate glass beads as 6.0 pounds per gallon of waterborne paint.

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: CSLB C-32 Exam Practice Questions - California CSLB C-32 Parking and Highway Improvement Examination Exam →