What document must a C-32 contractor submit to verify that traffic paint or thermoplastic material meets California VOC and environmental regulations?

  1. The manufacturer's Safety Data Sheet (SDS) and Technical Data Sheet (TDS).
  2. A notarized copy of the contractor's current state contractor license certificate.
  3. The municipal building inspector's personal sign-off signature card.
  4. A written guarantee of zero paint wear for a period of ten years.

Answer: A — The manufacturer's Safety Data Sheet (SDS) and Technical Data Sheet (TDS).

The correct answer is shown above. Try the full quiz for additional practice.