When installing preformed thermoplastic pavement legends (such as "STOP" or "ONLY"), how is the material fused to the asphalt substrate?

  1. Cold pressed onto the surface using a heavy 5-ton steel drum roller compactor.
  2. Heated in-place using a propane torch until the material melts and flows.
  3. Soaked in chemical solvent activator for 10 minutes prior to placement.
  4. Nailed down at 6-inch intervals using heavy galvanized masonry nails.

Answer: B — Heated in-place using a propane torch until the material melts and flows.

The correct answer is shown above. Try the full quiz for additional practice.