Practice question
When installing preformed thermoplastic pavement legends (such as "STOP" or "ONLY"), how is the material fused to the asphalt substrate?
- Cold pressed onto the surface using a heavy 5-ton steel drum roller compactor.
- Heated in-place using a propane torch until the material melts and flows.
- Soaked in chemical solvent activator for 10 minutes prior to placement.
- Nailed down at 6-inch intervals using heavy galvanized masonry nails.
Answer: B — Heated in-place using a propane torch until the material melts and flows.
The correct answer is shown above. Try the full quiz for additional practice.
Practice more: CSLB C-32 Exam Practice Questions - California CSLB C-32 Parking and Highway Improvement Examination Exam →