Practice question

Per NFPA 470 Chapter 12 JPRs, what is the IC's first command priority upon assuming command of a hazmat incident?

  1. Order decon setup
  2. Establish and announce command and conduct initial size-up
  3. Brief the media
  4. Request a Type 1 IMT

Answer: B — Establish and announce command and conduct initial size-up

The correct answer is shown above. Try the full quiz for additional practice.