Practice question

Which is true about cost tracking under ICS at a hazmat incident?

  1. Cost tracking is irrelevant
  2. Cost is tracked through Finance/Admin Section for reimbursement and cost recovery
  3. PIO tracks cost
  4. Operations Chief tracks cost

Answer: B — Cost is tracked through Finance/Admin Section for reimbursement and cost recovery

The correct answer is shown above. Try the full quiz for additional practice.

Practice more: Hazmat Incident Commander Practice Questions - NFPA 470 Hazardous Materials Incident Commander Certification Exam Exam →